Measure
Authors Zbur  
Coauthors: Calderon   Gipson  
Subject California Environmental Quality Act: electrical infrastructure projects.
Relating To relating to energy.
Title An act to add Chapter 8.5 (commencing with Section 2845) to Part 2 of Division 1 of the Public Utilities Code, relating to energy.
Last Action Dt 2025-04-23
State Amended Assembly
Status Died
Flags
Vote Req Approp Fiscal Cmte Local Prog Subs Chgs Urgency Tax Levy Active?
Majority No Yes Yes None No No Y
i
Leginfo Link  
Bill Actions
2026-02-02     From committee: Filed with the Chief Clerk pursuant to Joint Rule 56.
2026-01-31     Died pursuant to Art. IV, Sec. 10(c) of the Constitution.
2025-05-23     In committee: Held under submission.
2025-05-14     In committee: Set, first hearing. Referred to APPR. suspense file.
2025-04-24     Re-referred to Com. on APPR.
2025-04-23     Read second time and amended.
2025-04-22     From committee: Amend, and do pass as amended and re-refer to Com. on APPR. (Ayes 14. Noes 0.) (April 21).
2025-04-03     Coauthors revised.
2025-04-03     From committee: Do pass and re-refer to Com. on NAT. RES. (Ayes 17. Noes 0.) (April 2). Re-referred to Com. on NAT. RES.
2025-03-10     Referred to Coms. on U. & E. and NAT. RES.
2025-02-20     From printer. May be heard in committee March 22.
2025-02-19     Read first time. To print.
Versions
Amended Assembly     2025-04-23
Introduced     2025-02-19
Analyses TBD
Latest Text Bill Full Text
Latest Text Digest

The California Environmental Quality Act (CEQA) requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment. CEQA exempts certain projects from its requirements, including actions necessary to prevent or mitigate an emergency.

Existing law prohibits an electrical corporation from beginning the construction of a line, plant, or system, or extensions of those facilities without first obtaining from the Public Utilities Commission a certificate that the present or future convenience and necessity require or will require the construction. Existing law specifies that the certificate is not required for the extension, expansion, upgrade, or other modification of existing electrical transmission facilities.

This bill would require the commission to determine whether to certify the environmental impact report for an electrical infrastructure project that is a priority project, as defined, no later than 270 days after the commission determines that an application for an electrical infrastructure project is complete, except as specified. The bill would require a project applicant to identify an electrical infrastructure project that is a priority project and the basis for the designation in the application to the commission. The bill would require commission staff to review an application for a priority project no later than 30 days after it is filed and notify the applicant in writing of any deficiencies in the information and data submitted in the application. The bill would require the applicant to correct any deficiencies or notify the commission in writing why it is unable to correct those deficiencies, as specified, within 60 days of that notification. The bill would require the commission to deem an application for a priority project complete with a preliminary ruling setting the scope and schedule, as provided.

Under existing law, a violation of any order, decision, rule, direction, demand, or requirement of the commission is a crime.