Session:   
Updated:   2026-02-23

Bill Full Text

Home - Bills - Bill - Authors - Dates - Locations - Analyses - Organizations

<?xml version="1.0" ?>
<ns0:MeasureDoc xmlns:html="http://www.w3.org/1999/xhtml" xmlns:ns0="http://lc.ca.gov/legalservices/schemas/caml.1#" xmlns:ns3="http://www.w3.org/1999/xlink" xmlns:xsi="http://www.w3.org/2001/XMLSchema-instance" version="1.0" xsi:schemaLocation="http://lc.ca.gov/legalservices/schemas/caml.1# xca.1.xsd">
        


        <ns0:Description>
                <ns0:Id>20250AB__276299INT</ns0:Id>
                <ns0:VersionNum>99</ns0:VersionNum>
                <ns0:History>
                        <ns0:Action>
                                <ns0:ActionText>INTRODUCED</ns0:ActionText>
                                <ns0:ActionDate>2026-02-20</ns0:ActionDate>
                        </ns0:Action>
                </ns0:History>
                <ns0:LegislativeInfo>
                        <ns0:SessionYear>2025</ns0:SessionYear>
                        <ns0:SessionNum>0</ns0:SessionNum>
                        <ns0:MeasureType>AB</ns0:MeasureType>
                        <ns0:MeasureNum>2762</ns0:MeasureNum>
                        <ns0:MeasureState>INT</ns0:MeasureState>
                </ns0:LegislativeInfo>
                <ns0:AuthorText authorType="LEAD_AUTHOR">Introduced by Assembly Member Boerner</ns0:AuthorText>
                <ns0:Authors>
                        <ns0:Legislator>
                                <ns0:Contribution>LEAD_AUTHOR</ns0:Contribution>
                                <ns0:House>ASSEMBLY</ns0:House>
                                <ns0:Name>Boerner</ns0:Name>
                        </ns0:Legislator>
                </ns0:Authors>
                <ns0:Title> An act to amend Section 463 of the Public Utilities Code, relating to energy. </ns0:Title>
                <ns0:RelatingClause>energy</ns0:RelatingClause>
                <ns0:GeneralSubject>
                        <ns0:Subject>Electrical corporations and gas corporations: rates.</ns0:Subject>
                </ns0:GeneralSubject>
                <ns0:DigestText>
                        <html:p>Existing law vests the Public Utilities Commission with regulatory authority over public utilities, including electrical corporations and gas corporations. Existing law authorizes the commission to fix the rates and charges for every public utility and requires that those rates and charges be just and reasonable. Existing law requires the commission, for purposes of establishing rates for any electrical corporation or gas corporation, to disallow expenses reflecting the direct or indirect costs resulting from any unreasonable error or omission relating to the planning, construction, or operation of any portion of the corporation’s plant that cost, or is estimated to have cost, more than $50,000,000, including any expenses resulting from delays caused by any unreasonable error or omission, as specified.</html:p>
                        <html:p>This bill would make nonsubstantive changes
                to that requirement.</html:p>
                </ns0:DigestText>
                <ns0:DigestKey>
                        <ns0:VoteRequired>MAJORITY</ns0:VoteRequired>
                        <ns0:Appropriation>NO</ns0:Appropriation>
                        <ns0:FiscalCommittee>NO</ns0:FiscalCommittee>
                        <ns0:LocalProgram>NO</ns0:LocalProgram>
                </ns0:DigestKey>
                <ns0:MeasureIndicators>
                        <ns0:ImmediateEffect>NO</ns0:ImmediateEffect>
                        <ns0:ImmediateEffectFlags>
                                <ns0:Urgency>NO</ns0:Urgency>
                                <ns0:TaxLevy>NO</ns0:TaxLevy>
                                <ns0:Election>NO</ns0:Election>
                                <ns0:UsualCurrentExpenses>NO</ns0:UsualCurrentExpenses>
                                <ns0:BudgetBill>NO</ns0:BudgetBill>
                                <ns0:Prop25TrailerBill>NO</ns0:Prop25TrailerBill>
                        </ns0:ImmediateEffectFlags>
                </ns0:MeasureIndicators>
        </ns0:Description>
        <ns0:Bill id="bill">
                <ns0:Preamble>The people of the State of California do enact as follows:</ns0:Preamble>
                <ns0:BillSection id="id_2A23D191-C519-46B7-85DE-490BB0A2DD0F">
                        <ns0:Num>SECTION 1.</ns0:Num>
                        <ns0:ActionLine action="IS_AMENDED" ns3:href="urn:caml:codes:PUC:caml#xpointer(%2Fcaml%3ALawDoc%2Fcaml%3ACode%2Fcaml%3ALawHeading%5B%40type%3D'DIVISION'%20and%20caml%3ANum%3D'1.'%5D%2Fcaml%3ALawHeading%5B%40type%3D'PART'%20and%20caml%3ANum%3D'1.'%5D%2Fcaml%3ALawHeading%5B%40type%3D'CHAPTER'%20and%20caml%3ANum%3D'3.'%5D%2Fcaml%3ALawHeading%5B%40type%3D'ARTICLE'%20and%20caml%3ANum%3D'1.'%5D%2Fcaml%3ALawSection%5Bcaml%3ANum%3D'463.'%5D)" ns3:label="fractionType: LAW_SECTION" ns3:type="locator">
                                Section 463 of the
                                <ns0:DocName>Public Utilities Code</ns0:DocName>
                                 is amended to read:
                        </ns0:ActionLine>
                        <ns0:Fragment>
                                <ns0:LawSection id="id_E567D0FC-4B02-40B4-B985-668F290318AF">
                                        <ns0:Num>463.</ns0:Num>
                                        <ns0:LawSectionVersion id="id_00F0D3D4-F992-4629-AEAF-FA31B962AB69">
                                                <ns0:Content>
                                                        <html:p>
                                                                (a)
                                                                <html:span class="EnSpace"/>
                                                                For purposes of establishing rates for any electrical corporation or gas corporation, the commission shall disallow expenses reflecting the direct or indirect costs resulting from any unreasonable error or omission relating to the planning, construction, or operation of any portion of the corporation’s plant that cost, or is estimated to have cost, more than fifty million dollars ($50,000,000), including any expenses resulting from delays caused by any unreasonable error or omission.
                                  This section does not prohibit a finding by the commission of other unreasonable or imprudent expenses. This subdivision clarifies the existing authority of the commission, does not limit or restrict any power or authority of the commission conferred by any other law, and applies to all matters pending before the commission. This section does not prohibit the commission from establishing rates for an electrical
                                  corporation or gas corporation on a basis other than an allowed rate of return on undepreciated capital costs.
                                                        </html:p>
                                                        <html:p>
                                                                (b)
                                                                <html:span class="EnSpace"/>
                                                                Whenever an electrical corporation or gas corporation fails to prepare or maintain records sufficient to enable the commission to completely evaluate any relevant or potentially relevant issue related to the reasonableness and prudence of any expense relating to the planning, construction, or operation of the corporation’s plant, the commission shall disallow that expense for purposes of establishing rates for the corporation. This subdivision does not apply if the commission determines that a
                                  reasonable person could not have anticipated either the relevance or potential relevance, to an evaluation of costs incurred on the project, of preparing or maintaining the records or the extent of recordkeeping required to adequately evaluate those costs.
                                                        </html:p>
                                                        <html:p>
                                                                (c)
                                                                <html:span class="EnSpace"/>
                                                                For purposes of this situation, all of the following definitions apply:
                                                        </html:p>
                                                        <html:p>
                                                                (1)
                                                                <html:span class="EnSpace"/>
                                                                “Planning” includes, but is not limited to, activities related to the initial and subsequent assessments of the need for a plant construction project; the selection of contractors and the negotiation of contract provisions; certification; project organization; and site selection, including the investigation and interpretation of environmental factors
                                  such as seismic conditions and other external factors affecting the construction, operation, and safety of the plant.
                                                        </html:p>
                                                        <html:p>
                                                                (2)
                                                                <html:span class="EnSpace"/>
                                                                “Construction” includes, but is not limited to, activities related to engineering such as the development and use of specifications, drawings, and procedures; the preparation and use of construction plans, including blueprints; procurement activities; repairs, replacement, redesign, or repositioning of equipment and facilities; startup activities; and quality assurance and quality control activities.
                                                        </html:p>
                                                        <html:p>
                                                                (3)
                                                                <html:span class="EnSpace"/>
                                                                “Operation” includes, but is not limited to, activities related to decisions affecting the timing and nature of the use of the plant; dispatch and control activities and decisions; and plant operation, fuel loading, and maintenance.
                                                        </html:p>
                                                        <html:p>
                                                                (4)
                                                                <html:span class="EnSpace"/>
                                                                “Error” includes, but is not limited to, any action or
                                  direction
                                  that causes an avoidable (A) increase in the time required to bring the plant to full commercial operation, (B) change in the number or types of personnel or firms required to bring the plant to full commercial operation, (C) increase in the number of worker hours required to complete any portion of the plant construction project, or
                                  (D) change of equipment, configuration, design, schedule, or program.
                                                        </html:p>
                                                        <html:p>
                                                                (5)
                                                                <html:span class="EnSpace"/>
                                                                “Omission” includes, but is not limited to, any failure to act or to provide direction that causes an avoidable (A) increase in the time required to bring the plant to full commercial operation, (B)
                                  change in the number or types of personnel or firms required to bring the plant to full commercial operation, (C) increase in the number of worker hours required to complete any portion of the plant construction project, or (D) change of equipment, configuration, design, schedule, or program.
                                                        </html:p>